Welcome to OStack Knowledge Sharing Community for programmer and developer-Open, Learning and Share
Welcome To Ask or Share your Answers For Others

Categories

0 votes
833 views
in Technique[技术] by (71.8m points)

c# - Get date of first and last day of week knowing week number

I need to get the date of the first and last day of the week knowing the week number.

I get a start date and an end date, representing the first and last day of a selected week in a given year. then I need to get the start date and end date of the same week of the previous year to do a graphical comparison of some data.

I managed to get the week number based on the given start date and end date. Now I need to get the date of the first day and last day of the same week of the previous year. How could I do this quickest ?

EDIT: This is how I got the week number:

 private int GetWeekNumber(DateTime date)
    {
        GregorianCalendar calendar = new GregorianCalendar(GregorianCalendarTypes.USEnglish);
        return calendar.GetWeekOfYear(date, CalendarWeekRule.FirstDay, DayOfWeek.Sunday);            
    }
See Question&Answers more detail:os

与恶龙缠斗过久,自身亦成为恶龙;凝视深渊过久,深渊将回以凝视…
Welcome To Ask or Share your Answers For Others

1 Answer

0 votes
by (71.8m points)

You can use following two methods to calculate the week-number and the start-date of a given weeknumber according to a given year:

// this method is borrowed from http://stackoverflow.com/a/11155102/284240
public static int GetIso8601WeekOfYear(DateTime time)
{
    DayOfWeek day = CultureInfo.InvariantCulture.Calendar.GetDayOfWeek(time);
    if (day >= DayOfWeek.Monday && day <= DayOfWeek.Wednesday)
    {
        time = time.AddDays(3);
    }

    return CultureInfo.InvariantCulture.Calendar.GetWeekOfYear(time, CalendarWeekRule.FirstFourDayWeek, DayOfWeek.Monday);
} 

public static DateTime FirstDateOfWeek(int year, int weekOfYear, System.Globalization.CultureInfo ci)
{
    DateTime jan1 = new DateTime(year, 1, 1);
    int daysOffset = (int)ci.DateTimeFormat.FirstDayOfWeek - (int)jan1.DayOfWeek;
    DateTime firstWeekDay = jan1.AddDays(daysOffset);
    int firstWeek = ci.Calendar.GetWeekOfYear(jan1, ci.DateTimeFormat.CalendarWeekRule, ci.DateTimeFormat.FirstDayOfWeek);
    if ((firstWeek <= 1 || firstWeek >= 52) && daysOffset >= -3)
    {
        weekOfYear -= 1;
    }
    return firstWeekDay.AddDays(weekOfYear * 7);
}

Then you can get both dates in the following way:

// 46
int thisWeekNumber = GetIso8601WeekOfYear(DateTime.Today); 
// 11/11/2013  
DateTime firstDayOfWeek= FirstDateOfWeek(2013, thisWeekNumber, CultureInfo.CurrentCulture); 
// 11/12/2012  
DateTime firstDayOfLastYearWeek = FirstDateOfWeek(2012, thisWeekNumber, CultureInfo.CurrentCulture);   

Add 6 days to get the end of the week.


与恶龙缠斗过久,自身亦成为恶龙;凝视深渊过久,深渊将回以凝视…
Welcome to OStack Knowledge Sharing Community for programmer and developer-Open, Learning and Share
Click Here to Ask a Question

...