I need a Date.prototype.addBusDays function
that'll take an integer as the number of working days to add to the date.
However, there are two considerations: 1. Weekends, 2. Holidays (which I imagine would be a preset array to compare against. If beginning date and end date contain 3 holidays, then you push out the end date by 3)
I have come across some scripts online, one dilemma I can think of is, lets say you address all the weekends first, then you do the holidays, what if you +1 day (due to holiday), and your end date is pushed into a weekends again...<
Any ideas?
Thanks!
EDIT:
This is a part of a scheduling tool I am developing, which mean the dates will be tied to tasks which are linked together. Adding 1 day to a task, will trigger a recalculation of everything tied to it, potentially all dates in the database.