IIS already does this, that's what recycling is all about. IT's loading the DLL's while the old version of the application is still running. only after this is completed the recycling is complete.
However loading the DLL's is only part of getting web applications ready, there might also be initial loads like loading/caching the user db etc.
These actions are not part of the recycle process, they happen after all DLL's reloaded and the recycling is already completed.
A while back I ran into this issue with an application that had a huge startup time due to heavy db activity/caching during startup. So I was interested if there is some functionality that allows us to execute code before the recycle is marked as completed, so that the application is first considered recycled when everything is ready to run. Basically what I wanted is some kind of staging functionality.
I was in contact with the IIS team regarding this issue, sadly they told me that no such functionality exists, nor is it planned.
To solve this you could try do the following:
- Use alternating deploys:
You setup 2 Websites with separate application pools. One of them is the LIVE website the other one is the STAGED website. If you want to deploy changed you simply deploy to the STAGED website. After everything is loaded/cached etc. you switch the URL settings of the web applications to reroute incoming requests from the LIVE to the STAGED one. So the LIVE one becomes the new STAGED and the other way around. The next deploy would then go to the new STAGED again and so on.
UPDATE
Apparently they have created a IIS Module that provides this functionality by now:
IIS Application Warm-Up Module for IIS 7.5
The IIS team has released the first beta test version of the
Application Warm-Up Module for IIS 7.5. This makes warming up your
applications even easier than previously described. Instead of writing
custom code, you specify the URLs of resources to execute before the
Web application accepts requests from the network. This warm-up occurs
during startup of the IIS service (if you configured the IIS
application pool as AlwaysRunning) and when an IIS worker process
recycles. During recycle, the old IIS worker process continues to
execute requests until the newly spawned worker process is fully
warmed up, so that applications experience no interruptions or other
issues due to unprimed caches. Note that this module works with any
version of ASP.NET, starting with version 2.0.
For more information, see Application Warm-Up on the IIS.net Web site.
For a walkthrough that illustrates how to use the warm-up feature, see
Getting Started with the IIS 7.5 Application Warm-Up Module on the
IIS.net Web site.
See:
http://www.asp.net/whitepapers/aspnet4
If you use ASP.NET 4 Auto Start feature:
You can still choose to auto-recycle the worker processes from time to
time. When you do that, though, the app will immediately restart and
your warm up code will execute (unlike today - where you have to wait
for the next request to-do that).
The main difference between Warm Up and Auto Start feature is that the Warm Up Module is part of the recycling process. Rather than blocking the application for requests, while running the init code.
Only thing you get by using the Auto Start feature is that you don't have to wait for a user to hit the page, which does not help your case.
See the Gu's blog post:
http://weblogs.asp.net/scottgu/archive/2009/09/15/auto-start-asp-net-applications-vs-2010-and-net-4-0-series.aspx
UPDATE 2:
Sadly the Warmup Module has been discontinued for IIS 7/7.5:
http://forums.iis.net/t/1176740.aspx
It will be part of IIS8 though (It's now called Application Initialization Module):
http://weblogs.asp.net/owscott/archive/2012/03/01/what-s-new-in-iis-8.aspx
UPDATE 3:
As pointed out in the comments the Warmup Module resurfaced for IIS 7.5 as Application Initialization Module for IIS 7.5 after IIS 8 was released:
http://www.iis.net/downloads/microsoft/application-initialization